Construction 411

2019 Street Reconstruction & Street Rehabilitation Program

Check this web page for updates on  your street projects, which may include Street Reconstruction, Street Rehabilitation or Street Resurfacing.  If your street is on the list at the bottom of this page, please sign-up for email updates!

Update- Construction 411 - Streets

April 15, 2019 @ 10:30 a.m.

Waverly Drive – Windsor Drive to Crabtree Drive
Lampignano & Son Construction Company completed the concrete work on the north side of Waverly Dr.  All residents on the north side now have access to their driveways.

The concrete removal scheduled for Monday, April 15 has been cancelled.  This work has been rescheduled, weather permitting, to begin on Tuesday, April 16, 2019 on the south (odd addresses) side only. Concrete removal includes all curb and gutter, concrete driveway aprons, and intermittent sidewalk.  The curb is tentatively scheduled to be replaced on Thursday, April 18, 2019.  Concrete driveways and sidewalks will be replaced once the curb has been poured.  

The street removal phase of construction will begin once the concrete work is complete.

Canterbury Drive – Highland Avenue to Suffield Drive
Highland Avenue – Suffield Drive to Hintz Road
The Village of Arlington Heights completed construction layout and staking. Stakes are set three feet behind the proposed location of the curb and are used as an elevation guide during construction (they are not the location of the new back of curb).  Please do not disturb the construction stakes until after the curb has been poured. In addition, the contractor will call in J.U.L.I.E. locate to mark out the underground utilities, please leave the utility flags in place.

The concrete work on the north and east side is substantially complete.  Driveway access will be restored once the concrete has cured.  

The concrete removal for the south and west side is expected to begin Wednesday, April 17 or Thursday, April 18.  Residents will receive a notification once this date has been confirmed

Davis Street – Bristol Lane to Beverly Lane
Beverly Lane – Davis Street to Lynden Lane
Fairview Street – Lincoln Lane to Dryden Place

The street light relocation has been completed on Davis Street and Beverly Lane.  The anticipated completion of street light relocation on Fairview Street is Monday, April 15, 2019.

Concrete removal and replacement is tentatively scheduled to begin the week of April 22.  Residents will receive a notification once this date has been confirmed

Yale Avenue – White Oak Street to the South 
The Village of Arlington Heights completed construction layout and staking. Stakes are set three feet behind the proposed location of the curb and are used as an elevation guide during construction (they are not the location of the new back of curb).  Please do not disturb the construction stakes until after the curb has been poured. In addition, the contractor will call in J.U.L.I.E. locate to mark out the underground utilities, please leave the utility flags in place.

The contractor began sawcutting the pavement and this work is expected to continue into the week of April 15.

The water main installation scheduled to begin on Monday, April 15 has been cancelled.  This work will now begin, weather permitting, on Tuesday, April 16.

The new water main will be installed approximately four feet into the pavement along the east side of Yale Avenue.  Multiple water service interruptions will occur, but will be scheduled in advance.  All costumers that will be affected will be notified 24 hours in advance of the scheduled shut-off.  The duration of each water outage will not exceed 3 hours.

Access to driveways may be temporarily restricted during pipe laying operations; these driveway restrictions will be minimal.  The contractor will knock on doors to notify residents, if driveway access will be affected.  Once the work has been completed, the Contractor will place stone in the areas that have been removed to provide access to the driveway.  These residents may park on the street while this work is taking place.  Parking passes will not be required during this phase of construction.

During the construction, on-street parking on Yale Avenue within 500’ of water main installation will be prohibited between 7:00 a.m. and 4:00 p.m.

It is anticipated that the installation of the water main will be completed in 3-4 weeks.  For your convenience, we have provided a general sequence of construction activities for this phase of construction.  This schedule is an estimate and subject to change.
1. New water main pipe is installed – 5 to 7 working days
2. Chlorination and testing of new water main – 5 to 7 working days (minimal work will take place during this time.  Once the new main is approved work will resume.) 
3. Connecting residential water service lines to the new water main – 5 -7 working days 

Once the water main is completed, the street reconstruction activities will begin.  Another notification will be passed out prior to this work starting.
As a reminder, please mark the location of or move all sprinkler systems, dog fences, or landscaping that may be impacted during construction within Village right-of-way.

Campus Drive – Ridge Avenue to University Drive
Raleigh Street – Roanoke Drive to Wilke Drive
Huron Street – Verde Drive to Champlain Street
Frontenac Street – Champlain Street to Kennicott Avenue

No work has been scheduled at this time.  Please check back for updates.

2019 Street Reconstruction & Street Rehabilitation Program

The 2019 road construction season is under way in Arlington Heights! Check out this page for updates on your street projects, which may include Street Reconstruction, Street Rehabilitation or Street Resurfacing.  The Street Resurfacing Program is expected to be bid later this spring. Please check for construction updates below the list of streets. Also sign up to receive email updates affecting your street project!