Street Reconstruction

General Information 2022
Resume Construction Date: April 2023
Tentative Completion Date: October 2023
Contractor: Builder Paving LLC
Awarded Contract Amount: $4,240,000
Funding Source: Motor Fuel Tax (MFT)

General Information 2023
Tentative Start Date: April 2023
Tentative Completion Date: October 2023
Contractor: Builder Paving LLC
Awarded Contract Amount: $2,954,000
Funding Source: Motor Fuel Tax (MFT)

Newsletters & Notices
Types of notices provided are:
  • Mailed: Initial construction notices will be mailed to residents within the project limits.
  • Hand Delivered notices: before the start of each major work effort
  • Emailed: Reserved for urgent updates only
  • Website: As the project timeline progresses
Contact Information
Briget Schwab, P.E.
Phone: 847-368-5257
bschwab@vah.com

Project Description
Street Reconstruction - At this stage of deterioration, the curb and gutter is no longer functioning properly, subbase failure is observed, and the main part of the street is in poor condition.  The entire street is removed down to the subgrade including the curb and gutter.  The curb and gutter is installed and the street is replaced with full-depth asphalt.  This project may also require grade changes so the driveway approaches are completely removed and replaced from the sidewalk to the curb.  This project also includes intermittent sidewalk and drainage structure repair.
2022 Street Reconstruction Update from Previous Year
2023 Street Reconstruction Begins: March 2023